A disaster recovery plan that has never been executed is a hypothesis.

Most estates have the plan. Replication is configured, the recovery site has capacity, the runbook exists in a wiki, and the compliance checkbox is ticked annually by someone reviewing the document rather than running it. What is far rarer is a team that can say what happened the last time the workloads were actually brought up at the recovery site: which ones started, in what order, how long it took, and what broke.

That gap is usually blamed on time or on risk appetite. In practice it is a storage problem, and it has a precise shape. A rehearsal is only worth running if it is cheap, repeatable and genuinely non-destructive, and whether it is any of those three is decided almost entirely by what the storage layer can do with a replicated volume. On VMware® vSphere that question was answered for you by a button. After the exit it is answered by primitives you assemble yourself.

This post is about the rehearsal. It is deliberately not about who orchestrates the real failover when the site is actually down, which is a different question with a different answer and is covered in the Site Recovery Manager replacement post. Read that one for the orchestration half. It is also not about whether the backup copy contains usable data, which is a separate test against a different artifact and is covered in the backup validation post. This one is about proving the failover works before you need it.

What a test failover has to guarantee

Disaster recovery testing is the practice of bringing protected workloads up at the recovery site from replicated data, verifying they function, and then discarding the result, all without affecting production. A DR drill is one execution of that practice. A DR test plan is the written form of it: the scope, the order, the checks and the rollback.

The definition is easy. The guarantees underneath it are what make it hard, and there are four of them:

  1. The workloads start from the replicated copy, not from production data reached over a stretched network. A test that quietly mounts production volumes has proved nothing about the recovery site.
  2. They start on an isolated network. Duplicate IP addresses, duplicate cluster identities and duplicate service registrations are the fastest way to turn a rehearsal into the incident it was meant to prevent.
  3. Replication is never interrupted. If the drill requires you to break the replication relationship, reverse it, or pause it, then for the duration of the test you are unprotected, which means the drill itself has raised your risk.
  4. The recovery point survives the test. If the test consumes the latest replicated state, and a real outage happens during the rehearsal, you fail over to whatever the test left behind.

On vSphere, Site Recovery Manager delivered all four in one operation. The mechanism is worth stating precisely, because the replacement is only legible once you know what you are replacing. SRM asked the array for a writable snapshot of the already-replicated device, mounted that snapshot to the recovery hosts, attached the recovered VMs to an isolated port group, and powered them on in the order the recovery plan specified. The replication relationship itself was untouched throughout: the array kept receiving production writes into the real replica while the test ran against a copy-on-write view of it. Cleanup deleted the snapshot and the test VMs.

That is the whole trick. The test was cheap because the array could produce a writable view of replicated data without copying it, and because the platform had a first-class concept of a network nobody could reach.

After the exit, nothing supplies that as a single operation, but every piece of it still exists. The snapshot becomes a VolumeSnapshot of the replicated volume. The writable view becomes a PersistentVolumeClaim cloned from that snapshot, so test writes land somewhere discardable. The isolated port group becomes a namespace plus a NetworkPolicy that denies egress and ingress to everything outside it. The recovery plan becomes the workload or VirtualMachine definitions applied against the cloned claims. The cleanup becomes deleting the namespace.

The drill, step by step

The order matters more than any individual step, because each step is only meaningful if the one before it actually succeeded. A clone taken from a snapshot nobody verified is a clone of unknown data. A boot sequence run against volumes with unrelated recovery points proves only that the VM posts.

Run it in this order, and treat each verification as a gate rather than a log line.

StepPreconditionVerificationRollback
1. Freeze a recovery pointReplication is current and its lag is within the stated RPOSnapshot timestamps across every volume in one application fall inside one consistency windowDelete the snapshot set; replication was never touched
2. Clone the snapshotsThe storage layer can present a writable clone without copying the volumeClone creation returns in seconds and consumes near-zero capacityDelete the clones; the snapshots and the replica remain
3. Build the isolation boundaryA dedicated namespace exists with default-deny ingress and egressA pod in the namespace cannot resolve or reach any production endpointDelete the namespace
4. Start the workloads in orderDependency order and boot sequencing are written down, not rememberedEach tier reaches a real readiness check, not just a running stateScale to zero; nothing outside the namespace was touched
5. Prove and destroyApplication-level checks exist that a human did not have to interpretTransactions complete against the recovered copy, and results are recordedDelete the namespace and the clones; verify capacity returns

Table 1: The five stages of a DR drill, with the gate each one has to pass and the rollback that leaves production untouched.

Five stages of a disaster recovery drill, each with the state it produces and the failure it hides
Figure 1: The drill in order, with the failure mode each stage conceals if its verification is skipped.

Two of these steps deserve more than a table row.

Step 1 is where multi-tier applications are won or lost. Replication moves blocks. It does not recreate Kubernetes objects, rebind claims, or start workloads in order, and it has no idea which volumes belong to the same application. If each volume replicates independently, each one arrives at the recovery site with its own recovery point. For a multi-disk VM whose operating system disk and data disk land seconds apart, that is often a guest that does not boot. The drill is the only thing that will tell you this, and it will tell you at step 4 rather than step 1 unless you check the timestamps deliberately. Group snapshots, where the storage layer freezes a set of volumes at one point in time, are what make this a non-issue rather than a recurring surprise.

Step 2 is the economics of the whole exercise. A rehearsal that requires a full copy of the protected data is a rehearsal that needs a maintenance window, a capacity reservation and an approval. It will be run once. A rehearsal where the writable copy is a metadata operation against an existing snapshot can be run quarterly, or after every significant change, which is the only cadence at which a DR plan stays true. The difference between those two drills is not procedural discipline. It is whether the storage layer implements clone as a reference or as a copy.

Where the drill breaks, and what each break is telling you

A failed drill is a success. It is considerably cheaper to discover these during a rehearsal than during an outage, and each failure points at a specific missing piece rather than at general unreadiness.

The test workloads answer on production addresses. The isolation boundary was a namespace and nothing else. Namespaces are an RBAC and naming boundary, not a network one: without an explicit default-deny NetworkPolicy, pods in a fresh namespace can reach everything the cluster can reach. If the recovered application re-registers itself with a production service discovery endpoint, the drill has just pointed live traffic at a copy.

The guest boots and the application does not. Almost always a consistency problem rather than a replication problem. The blocks arrived; they arrived from different moments. This is also where crash-consistent and application-consistent part company, and the distinction is covered properly in the guest quiescing post.

The clone takes hours. The storage layer is copying. At that point the honest conclusion is that quarterly rehearsal is not available to you on this architecture, and the plan should say so rather than pretending otherwise.

Everything starts, nothing talks. Dependency ordering and IP re-addressing were in somebody’s head. No storage layer supplies these, and no snapshot mechanism will ever surface them. They belong in the test plan.

Capacity does not come back after cleanup. Clones were deleted but their parent snapshots were not, or retention policy is holding them. Worth catching early: a team that runs drills quarterly and never reclaims the space will eventually stop running drills.

What the storage layer owes you, and what it does not

The split is clean, and being honest about it is more useful than claiming the whole problem.

simplyblock supplies the three primitives the rehearsal rests on. A snapshot of a replicated volume, taken across a group of volumes at one point in time so a multi-disk application gets one recovery point rather than several. A writable clone created from that snapshot as a metadata operation, so the copy that the drill writes into costs effectively nothing and appears in seconds. And cross-cluster replication that the test never has to touch, because the drill reads a snapshot rather than the live replication target. Those capabilities are part of the platform rather than a separately licensed data-protection tier, which matters here mostly because a drill you have to buy a licence to run is a drill that gets deferred.

simplyblock does not supply dependency ordering, boot sequencing, IP re-addressing, or the runbook. It will not tell you that the message broker has to be healthy before the API tier starts, and it cannot know which DNS records need to change. A storage layer that clones cheaply makes a rehearsal affordable. It does not make a plan correct. That half is orchestration, and it belongs with the tooling discussed in the SRM replacement post and in the broader open source disaster recovery tooling roundup.

It is worth knowing where the common alternatives sit on the first half. Red Hat® OpenShift® Data Foundation can produce volume snapshots and clones through the standard CSI interfaces, so the shape of the drill above is available there too. The constraints are different rather than absent: metro synchronous and regional asynchronous replication, and VM-level DR orchestration, sit behind ODF Advanced, which is a separate per-two-core licence included in neither OpenShift Container Platform nor OpenShift Platform Plus, and VM-level orchestration additionally requires RHACM. Backup and restore capabilities ship in the simplyblock platform and in neither ODF edition. Those comparisons are drawn from simplyblock’s own capability analysis based on publicly available information as of September 2026, and are not independently verified. Ceph remains a good option when performance is not the main goal, and the drill procedure above works against it unchanged.

The practical recommendation is narrow. Before the next rehearsal, measure one thing: how long it takes to produce a writable copy of a replicated volume and how much capacity that copy consumes. If the answer is seconds and nothing, you can rehearse as often as the plan changes. If it is hours and a full copy, the frequency of your drills has already been decided for you, and no amount of planning discipline will change it. For the ongoing operational side of this after migration, Day 2 storage operations after the VMware exit covers the surrounding practice, and CSI snapshot architecture covers the policy design that makes retention predictable.

Questions and Answers

What is disaster recovery testing?

Disaster recovery testing is the practice of bringing protected workloads up at a recovery site from replicated data, verifying they actually function, and then discarding the result, all without interrupting production or consuming the recovery point you would need in a real outage. A single execution of it is a DR drill. The written form, covering scope, order, verification gates and rollback, is a DR test plan. Reviewing documentation is not testing; nothing is tested until something boots.

How often should you run a DR drill?

As often as the plan changes, which for most platform teams means quarterly plus after any significant architectural change. That cadence is only achievable if the rehearsal is cheap, and whether it is cheap is a storage property rather than a scheduling one. With simplyblock, the writable copy the drill runs against is a clone created from a snapshot as a metadata operation, so it appears in seconds and consumes effectively no capacity, which is what makes a quarterly drill realistic rather than aspirational. If each rehearsal requires a full copy of the protected data, expect it to happen once.

What goes in a DR test plan?

Five things, in order: the recovery point you are testing from and how you verify its consistency across every volume in an application; the isolation boundary and how you prove nothing can reach production from it; the dependency order in which workloads must start; the application-level checks that constitute success, written so a human does not have to interpret them; and the rollback, including reclaiming the capacity the test consumed. The storage layer supplies the primitives for the first and the last. The middle three are yours.

Does a test failover interrupt replication?

It should never need to. A correctly constructed drill reads from a snapshot of the replicated volume and runs against a clone of that snapshot, so the replication relationship keeps receiving production writes untouched for the entire duration of the test. If your procedure requires breaking, pausing or reversing replication to run a rehearsal, you are unprotected while rehearsing, which inverts the point of the exercise. That is a strong signal that the test is being run against the replication target itself rather than against a copy of it.

Is a successful DR drill proof that the plan works?

It is proof that the plan worked for the scope you tested, at the scale you tested, with the dependencies that existed on that day. That is considerably more than most estates have, and it is still not a guarantee. The common gap is scale: a drill that recovers three applications says little about recovering sixty simultaneously, where contention for recovery-site capacity and network bandwidth becomes the binding constraint. Record what you did not test as deliberately as you record what you did.

You may also like:

NVMe/TCP vs NVMe/RoCE for Kubernetes Storage: Choosing the Right Fabric
NVMe/TCP vs NVMe/RoCE for Kubernetes Storage: Choosing the Right Fabric

NVMe over Fabrics gives Kubernetes clusters low-latency block storage over the network. The transport you pick, TCP or RoCE, determines your latency floor, infrastructure cost, and operational complexity. Here is how to choose.

Ephemeral Storage in Kubernetes: Why It Silently Breaks Stateful Workloads
Ephemeral Storage in Kubernetes: Why It Silently Breaks Stateful Workloads

emptyDir and other ephemeral storage look fast and simple, until a pod eviction or node failure erases the data. Here is what actually happens, and how NVMe/TCP persistent volumes give you the same latency without the risk.

We Break Our Storage So You Never Have To